George Hank, CEO of Walker Construction has an opportunity to bid on a contract that pays $5,500 upon completion, but the contract calls for a late performance penalty of $140 per week for each week that the project is delayed beyond eight weeks.Find the crash cost per week for each activity and determine what are the total normal costs for the project?