9. A wholesale grocery distribution center uses a two-step process to fill orders. Tomorrow’s work will consist of filling the seven orders shown. Determine a job sequence that will minimize the time required to fill the orders.
TIME (hours)
Order
Step 1
Step 2
A
1.20
1.40
B
0.90
1.30
C
2.00
0.80
D
1.70
1.50
E
1.60
1.80
F
2.20
1.75
G
1.30
1.40