The partially completed inventory record for the drive shaft subassembly in the table below shows gross requirements, scheduled receipts, lead time, and current on-hand inventory.
a. Complete the last three rows of the record for an FOQ of 60 units. (Enter your responses as integers. A response of “0” is equivalent to being not applicable.)
Item: Driveshaft subassembly Lot Size:
FOQequals=60 units
Lead Time: 3 weeks
Week
1
2
3
4
5
6
7
8 Gross
requirements
30
25
20
25
45
45
40
40 Scheduled
receipts
75 Projected on-hand
inventory
15 Planned
receipts
Needs help with similar assignment?
We are available 24x7 to deliver the best services and assignment ready within 3-4 hours? Order a custom-written, plagiarism-free paper

